Power station projects

New Coal Fired Power Station, Lünen, Germany

Description

Trianel GmbH, a group of local utilities and energy providers, contracted a consortium consisting of Siemens PG, AE&E together with plant engineers IAI for the construction of a new 750MW coal fired power station in Lünen. Phase 1 design and subsequent construction was commenced by Codema in early Summer 2008. This consisted of deep foundations together with the major part of the infrastructure design. Phase 2 design and subsequent construction of the building works commenced in Autumn 2008. The power station is due to go online in 2012.
Coal Fired Power Station Lünen

Client

Siemens Energy, AE&E

Contractor

TRIANEL

Project location

Lünen

Project duration

2008 - 2011

Services

  • Structural engineering (reinforced concrete and structural steelwork)
  • Architectural design of buildings
  • Roads and landscaping
  • Utilities and drainage design